Civil Engineering (SSC JE) Notes

Construction Management for SSC JE Civil: CPM, PERT, Float, Bar Charts, Tenders, Contracts and Construction Equipment

Rahul Kumar

SSC Exam Expert & Content Editor

Updated 21 Oct 2026

PDF Notes: Construction Management for SSC JE Civil: CPM, PERT, Float, Bar Charts, Tenders, Contracts and Construction Equipment

Premium PDF · one-time payment of ₹5 · instant access

Construction management deals with the planning, scheduling and control of a project and with the contract system. SSC JE Civil asks questions on CPM and PERT, float, bar charts, the types of contracts and the tender procedure. This guide on construction management for SSC JE covers all of them, with solved examples, practice questions and FAQs.

Project Planning and Scheduling

Technique Features
Bar chart (Gantt chart) Developed by Henry Gantt (1917); shows the activities as horizontal bars against time; simple but does not show the interdependence of activities
Milestone chart Shows the key events of a project
Network techniques (CPM and PERT) Show the logical relationships between activities; used for large projects
Line of balance Used for repetitive work such as housing and roads

CPM and PERT

Feature CPM PERT
Full form Critical Path Method Programme Evaluation and Review Technique
Origin DuPont, USA (1957) US Navy, for the Polaris missile project (1958)
Time estimates One estimate (deterministic) Three estimates (probabilistic): optimistic, most likely and pessimistic
Orientation Activity-oriented Event-oriented
Use Construction projects where time is well known Research and development projects with uncertain time
Cost Time–cost trade-off (crashing) is a part of it Mainly concerned with time

Network Terms

Term Meaning
Activity A task that needs time and resources; shown by an arrow in the Activity-on-Arrow (AOA) network
Event (node) The start or the end of an activity; consumes no time
Dummy activity Has no duration; shown by a dashed arrow; used to show the logic
Critical path The longest path through the network; it decides the minimum duration of the project; the activities on it have zero total float
Earliest start time (EST) The earliest time an activity can start (forward pass)
Latest start time (LST) or latest finish time (LFT) The latest time without delaying the project (backward pass)
Total float LST − EST (or LFT − EFT); the time by which an activity can be delayed without delaying the project
Free float The delay possible without affecting the earliest start of the next activity
Independent float The delay possible without affecting any other activity, even if the preceding activity ends late
Slack The float of an event in PERT
Crashing Reducing the time of the activities by adding resources at a higher cost

PERT Time Estimates

  • Expected time te = (to + 4tm + tp) / 6 (beta distribution), where to is optimistic, tm the most likely and tp the pessimistic time.
  • Variance = ((tp − to) / 6)² and the standard deviation = (tp − to) / 6.
  • The standard deviation of the project is the square root of the sum of the variances of the activities on the critical path.
  • The probability of completing the project by a given time is found using the normal distribution Z = (Ts − Te) / σ.

Contracts

Type of Contract Features
Lump sum (fixed price) A fixed total price for the whole work; the contractor bears the risk
Item rate (unit price) contract The contractor quotes a rate per unit of each item; payment is based on the actual quantities
Percentage rate contract Quote as a percentage above or below the estimate
Cost plus contract The contractor is paid the actual cost plus a fee (fixed, percentage or sliding scale); used when the work cannot be defined in advance
Labour contract Only labour is supplied by the contractor; the material is supplied by the owner
Turnkey contract The contractor does the design, construction and handing over of a ready-to-use project (EPC and design-build)
Piece-work contract Payment per piece or unit of work
BOT (Build, Operate and Transfer) The contractor builds, runs for a period and then transfers to the owner

Tender Procedure

  1. Preparation of the estimate and the tender documents.
  2. Invitation of the tender (notice inviting tender, NIT) through newspapers or e-procurement.
  3. Submission of the tenders by the contractors with the earnest money deposit (EMD), generally 1–2% of the estimated cost.
  4. Opening of the tenders and comparison of the rates; selection of the lowest responsive bidder.
  5. Award of the contract, security deposit (generally 5–10% of the contract value, which includes the performance guarantee), and signing of the agreement.
  6. Issue of the work order and starting the work.

Documents and Bills

Document Purpose
Measurement Book (MB) Records the measurements of the work done; the basis of payment
Muster roll Attendance and wages of the daily labour
Running Account (RA) bill Interim payments during the work
Final bill Payment after completion of the work
Completion certificate Issued after the work is complete
Defect liability period The period after completion in which the contractor must repair the defects
Retention money A part of the bill kept back as a security
Arbitration Settlement of disputes through an arbitrator under the Arbitration and Conciliation Act, 1996

Construction Equipment (Selected)

Equipment Use
Bulldozer Pushing and levelling the earth
Scraper Excavating, hauling and spreading the earth
Grader Finishing and levelling surfaces; used in road construction
Dragline Excavation below the machine level and underwater
Power shovel Excavation above the machine level
Backhoe (hoe) Digging trenches and below the ground level
Roller Compaction of soil and bituminous layers
Transit mixer Carries ready-mix concrete
Tower crane Lifting materials in high-rise buildings

Safety on Construction Sites

  • Use of helmets, safety shoes and harnesses.
  • Scaffolding and barricading of excavations.
  • Safety rules are given in the Building and Other Construction Workers Act, 1996 and the BIS codes (IS 7969).
  • The use of the first aid box and fire-fighting equipment.

Solved Examples

Example 1. For an activity, the optimistic time is 4 days, the most likely 6 days and the pessimistic 14 days. Find the expected time.
te = (4 + 24 + 14)/6 = 7 days.

Example 2. Find the variance of the same activity.
((14 − 4)/6)² = (1.667)² = 2.78.

Example 3. An activity has an EST of 5 days and an LST of 9 days. Find its total float.
9 − 5 = 4 days.

Example 4. What is the total float of the activities on the critical path?
Zero.

Quick Tips

  • Memorise the PERT formulas te and the variance.
  • Remember that the critical path has zero float and is the longest path.
  • Learn the difference between CPM and PERT.
  • Learn the main types of contracts with one feature each.

Quick Revision Points

  • The critical path is the longest path with zero float.
  • Total float = LST − EST.
  • PERT: te = (to + 4tm + tp)/6.
  • CPM is deterministic; PERT is probabilistic.
  • EMD is usually 1–2% and security deposit 5–10%.

Practice Questions With Answers

  1. What does the critical path represent?
    Answer: The longest path and the minimum project duration
  2. What is the total float of critical activities?
    Answer: Zero
  3. What is the formula for the expected time in PERT?
    Answer: (to + 4tm + tp)/6
  4. Who developed the bar chart?
    Answer: Henry Gantt
  5. Which contract pays the actual cost plus a fee?
    Answer: Cost plus contract
  6. What is the EMD?
    Answer: Earnest money deposit
  7. Which book records the measurements of work done?
    Answer: Measurement Book
  8. Which technique uses three time estimates?
    Answer: PERT
  9. Which machine is used for digging below the machine level (trenches)?
    Answer: Backhoe (or dragline)
  10. What is the total float?
    Answer: LST − EST

How to Practise This Chapter

Practise 10 questions every day and write the steps on paper. Then attempt timed sets from our practice papers and the previous year papers page. See all topics on the Civil Engineering notes page, read the previous topic Irrigation Engineering and Hydrology.

Frequently Asked Questions

What is CPM?

The Critical Path Method, a network technique with a single time estimate for each activity.

What is PERT?

Programme Evaluation and Review Technique, a network technique with three time estimates.

What is the critical path?

The longest path in the network which decides the minimum project time.

What is float?

The spare time available to an activity without delaying the project.

What is a dummy activity?

An activity with zero duration used to show the logical dependence.

What is a bar chart?

A chart showing the activities as bars against time, developed by Henry Gantt.

What is a lump sum contract?

A contract at a fixed total price for the whole work.

What is an item rate contract?

A contract in which rates are quoted for each item and payment is for the quantities actually done.

What is EMD?

Earnest money deposit paid with the tender as a guarantee.

What is the Measurement Book?

The record of measurements of the work done by the contractor.

Is this topic asked in SSC JE?

Yes. Construction management is asked in SSC JE Civil.

What is crashing?

Reducing the project time by increasing the resources at extra cost.